Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is
tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to
Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum,
competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by
employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision
of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with
no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the
"normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between
October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs
the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for
Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?
Which of the following are NOT normally included in the project scope statement, either directly or by
reference?