During Timebox A, the Local Planning Authority Officer was sometimes asked to attend the Daily Stand-up
meeting as a temporary Specialist team member, to represent
any Planning Authority issues.
Is this an appropriate application of Agile Project Management for this project?
Once the change of priority has been approved, who is then responsible for including the requirement for a
secondary exit from the upstairs of the building to the Timebox
Plan for Timebox B?
During Timebox B, the 'Hoy for Hoy Hall'Action Group disagreed about the planned outcome of the Timebox.
The Project Manager organised a Facilitated Workshop to reengage this group and explore discrepancies in understanding.
Is this an appropriate application of Agile Project Management for this project?