Free Test Prep CCP Exam Questions

Absolute Free CCP Exam Practice for Comprehensive Preparation 

  • Test Prep CCP Exam Questions
  • Provided By: Test Prep
  • Exam: AACE Certified Cost Professional (CCP)
  • Certification: AACE
  • Total Questions: 191
  • Updated On: Jul 25, 2026
  • Rated: 4.9 |
  • Online Users: 382
Page No. 1 of 39
Add To Cart
  • Question 1

    • The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. 9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current schedule performance index (SPI)? 


      Answer: B
  • Question 2
    • An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. If $100,000 is needed to purchase a piece of equipment 3 years from now, how much money needs to be invested today assuming a 10% rate of return (rounded to the nearest thousand)? 


      Answer: C
  • Question 3
    • A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Which of the following percent complete measurement techniques is best suited for long-term non-production accounts (such as overhead accounts)? 


      Answer: A
  • Question 4
    • The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as: 

      Answer: A
  • Question 5

    • The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)


      Answer: B
PAGE: 1 - 39
Add To Cart

© Copyrights DumpsEngine 2026. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsEngine.