Activities in a project are discussed in a Work Breakdown Structure (WBS) session during theplanning phase. Team members inform the project manager that whilst estimating the duration foractivities, a lot of data exist about the effort required for each of them. Which estimation techniqueis best considered?
Activities in a project are discussed in a Work Breakdown Structure (WBS) session during theplanning phase. Team members inform the project manager that whilst estimating the duration foractivities, a lot of data exist about the effort required for each of them. Which estimation techniqueis best considered?