You are using networks and external activities in your project The purchase requisition has been created. What is the sequence for the following business transactions and documents?
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?