As a ScrumMaster, you notice that the team is struggling to complete their work within the sprint time box. The team has already identified several impediments that are preventing them from delivering the sprint goal. What should you do in this situation?
During the Daily Scrum, a team member claims that a particular task is not related to the current Sprint Goal and wants to remove it from the sprint backlog. What should the Scrum Master do?
During product backlog refinement, the Development Team and the Product Owner have identified a high-priority feature that needs to be added to the product. The feature is estimated to be a large effort and will take multiple sprints to complete. What should the development team do?