Free CMAA Construction-Manager Exam Questions

Absolute Free Construction-Manager Exam Practice for Comprehensive Preparation 

  • CMAA Construction-Manager Exam Questions
  • Provided By: CMAA
  • Exam: Certified Construction Manager (CCM)
  • Certification: CMAA Certified Professional
  • Total Questions: 66
  • Updated On: Sep 22, 2026
  • Rated: 4.9 |
  • Online Users: 132
Page No. 1 of 14
Add To Cart
  • Question 1
    • Which schedule process determines the earliest times that schedule activities can start and Finish, and the total project duration?


      Answer: B
  • Question 2
    • Which of the following contract types limits the potential incentive to increase profit through increasing contract costs?

      Answer: C
  • Question 3
    • The general contractor on a $1.2 billion terminal at an airport finds out that, due to supply chain issues, there is a 60% risk that they will not be able to get steel onsite for 10 weeks. The late start date of steel installation is four weeks away. Such a delay would cost the owner $75,000 per week to recover. What is the expected monetary value of risk?

      Answer: D
  • Question 4
    • The contract documents normally require which party/parties to coordinate the transfer of spare parts and warranties to the owner?

      Answer: A
  • Question 5
    • Owner's representation staff are managing the construction of a new water treatment plant. The owner has specific operational and sustainability goals they want met and are contracting the team for full commissioning services. The commissioning plan should include which of the following requirements for each party in the commissioning process?


      Answer: D
PAGE: 1 - 14
Add To Cart

© Copyrights DumpsEngine 2026. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsEngine.