When calculating the power demand of a UPS (Uninterruptible Power Supply)
system, only the backend capacity needs to be considered, and redundancy for the load does not
need to be accounted for, while the capacity of the battery can be ignored.
According to GB50174-2017, data centers using chilled water cooling systems should have
thermal storage devices, with storage time meeting operational needs. Is this correct?