Your project team has identified several potential risks on your current project that could have a significant impact if they occurred. The team examined the impact of the risks by keeping all the uncertain elements at their baseline values. What type of diagram will the team use to display this information?
If a risk has a 20 percent chance of happening in a given month, and the project is expected to last five months, what is the probability that this risk event will occur during the fourth month of the project?
You are a project manager for Giraffe Enterprises. You've recently taken over for a project
manager who lied about his PMI certification and was subsequently fired. Unfortunately, he did a
poor job of scope definition. Which of the following could happen if you don't correct this?
You are the project manger for Xylophone Phonics. This company produces children's software programs that teach basic reading and math skills. You are ready to assign project roles, responsibilities, and reporting relationships. Which project Planning process are you working on?