During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do?
A product owner obtains customer confirmation on product requirements and provides them to the team.
After explaining the user stories, the product owner receives agreement for acceptance from the team.
What should the team do next?
A team member on a new scrum project previously provided support to another application Due to issues with that application, the team member's former supervisor continues assigning them tasks related to that project. The new project's scrum master includes this issue in the risk register. What should the scrum master do next?
An agile team is working on the first sprint, and have already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?
© Copyrights DumpsEngine 2025. All Rights Reserved
We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsEngine.