Free PMI PMI-CP Exam Questions

Absolute Free PMI-CP Exam Practice for Comprehensive Preparation 

  • PMI PMI-CP Exam Questions
  • Provided By: PMI
  • Exam: Construction Professional in Built Environment Projects
  • Certification: PMI Built Environment
  • Total Questions: 177
  • Updated On: Dec 06, 2025
  • Rated: 4.9 |
  • Online Users: 354
Page No. 1 of 36
Add To Cart
  • Question 1
    • A construction professional was assigned to manage the planning and execution of structural aspects in a mega project involving the development of a high-speed railway network spanning multiple cities. The construction professional used the Project Interface Risk Impact (PIRI) matrix as a high-level decision-making guide to identify the extent of IM implementation required for the project and found out that the project falls under the High Complexity and Risk/High Impact cell.

      What IM maturity stage should the project aim to attain?


      Answer: B
  • Question 2
    • While controlling the project execution, the construction professional uncovers scope creep caused by a key stakeholder. When checking the Stakeholder Engagement Assessment Matrix, the construction professional finds out that the stakeholder is classified as “committed”.

      What should the construction professional do?


      Answer: C
  • Question 3
    • Upon the increasing number of accidents in a large construction project that employs hundreds of workers, the steering committee decides to track the locations of everyone on the field to ensure quick interventions.

      What technology should the construction professional use in order to implement the steering committee decision?


      Answer: B
  • Question 4
    • A construction professional receives a document from the client outlining the requirements for a project to revamp an aging office building. While reviewing the document, the construction professional finds certain requirements unclear and struggles to interpret some of the shop drawings.

      What should the construction professional do next?


      Answer: B
  • Question 5
    • A construction professional is asked to execute a power plant project using the Last Planner System® approach. What are the five connected conversations of LPS

      Answer: A
PAGE: 1 - 36
Add To Cart

© Copyrights DumpsEngine 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsEngine.