Free PMI PMI-CP Exam Questions

Absolute Free PMI-CP Exam Practice for Comprehensive Preparation 

  • PMI PMI-CP Exam Questions
  • Provided By: PMI
  • Exam: Construction Professional in Built Environment Projects
  • Certification: PMI Built Environment
  • Total Questions: 177
  • Updated On: Nov 25, 2025
  • Rated: 4.9 |
  • Online Users: 354
Page No. 1 of 36
Add To Cart
  • Question 1
    • A construction professional discovers a serious threat to the project; one of the project contractors might declare bankruptcy. If that happens, the project will be delayed for another two months.

      What should the construction professional do to mitigate the risk?


      Answer: D
  • Question 2
    • A construction professional is managing a hospital construction project. The project was contracted under a Design-Bid-Build delivery method with lump-sum contracts. The lump-sum contracts incentivized cost-cutting, which led to disagreements between the design and construction teams about material specifications and design changes. These issues caused delays, miscommunication, and frustration among stakeholders. Recognizing these challenges, the construction professional decides to adopt a more collaborative approach in future projects.

      What should the construction professional do in the future to avoid these challenges?


      Answer: D
  • Question 3
    • A construction professional is tasked with leading a meeting to address significant delays impacting the project timeline. With stakeholders, team leads, and key contributors expected to attend, the meeting must tackle several complex issues requiring focused discussion and clear decision-making. The construction professional aims to keep the meeting productive, ensuring each topic is addressed thoroughly while maintaining participant engagement and focus.

      What should the construction professional prioritize to lead the meeting effectively?


      Answer: B
  • Question 4
    • A construction professional is overseeing the construction of a city bridge project using a predictive approach. The project sponsor expresses disappointment with the progress, claiming that a critical structural component was overlooked. Despite having approved all project stages so far, the sponsor has asked the construction professional to put the project on hold while they reassess the situation.

      To resolve the issue and reach an agreement, the construction professional decided to use arbitration and mediation as: (Select two)


      Answer: A,E
  • Question 5
    • An organization is running a construction megaproject with over 100 interfaces. As it faced some issues in IM implementation, the organization requested the advice of a senior construction professional. After assessing the existing IM implementation, the construction professional recommended the organization to set up a single centralized document to easily review the status of all Interface Agreements (IA).

      What document does the construction professional refer to?


      Answer: C
PAGE: 1 - 36
Add To Cart

© Copyrights DumpsEngine 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsEngine.