Free PMI PMI-RMP Exam Questions

Absolute Free PMI-RMP Exam Practice for Comprehensive Preparation 

  • PMI PMI-RMP Exam Questions
  • Provided By: PMI
  • Exam: PMI Risk Management Professional
  • Certification: PMI Risk Management Professional
  • Total Questions: 267
  • Updated On: Nov 24, 2025
  • Rated: 4.9 |
  • Online Users: 534
Page No. 1 of 54
Add To Cart
  • Question 1
    • In reviewing the team's identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project's incentive payment for early completion. In implementing this plan, which response should the risk manager use?


      Answer: A
  • Question 2
    • A risk management team has completed a quantitative analysis, and the individual score in terms of schedule and cost has been identified. The team is consolidating inputs for contingency planning and notices that the available time and funds are not sufficient for all the risks. What should the risk manager advise the project team?


      Answer: D
  • Question 3
    • Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?


      Answer: B
  • Question 4
    • A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves. What should the risk manager do to mitigate the chance of the same issues reoccurring?


      Answer: D
  • Question 5
    • During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger? 


      Answer: A
PAGE: 1 - 54
Add To Cart

© Copyrights DumpsEngine 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsEngine.