Mary is the project manager for her organization. She is working with the project team to
define the project activities. She is concerned about some of the dependencies of the
project work, which may affect the project schedule. Which one of the following is the best
example of a project constraint that will likely affect the project's ability to finish by a given
deadline?
You are the project manager of the NHQ project. Your project has a budget of $1,258,456,
and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project,
you have spent $525,000. Management needs a performance report regarding the NHQ
project. Management is concerned that this project will be over budget upon completion.
Management would like to create a report telling them how much more the project will need
to complete. What value should you tell management?
You are the project manager of the GHY Project. This project is scheduled to last for one
year and has a BAC of $4,500,000. You are currently 45 percent complete with this project,
though you are supposed to be at your second milestone which accounts for half of the
project completion. There have been some errors in the project which has caused you to
spend $2,073,654. What is this project's schedule performance index?
You work as a project manager for BlueWell Inc. Your project requires the project team to
paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4
hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of
the hotel rooms. What type of an estimate are you creating in this scenario?
John works as a project manager of the NHQ Project. He has created the project network
diagram as shown in the figure:
Based on the project network diagram, how much float is available for Activity H if Activity B
is delayed by four days and Activity E is delayed by two days?