Free PMI PMI-SP Exam Questions

Absolute Free PMI-SP Exam Practice for Comprehensive Preparation 

  • PMI PMI-SP Exam Questions
  • Provided By: PMI
  • Exam: PMI Scheduling Professional
  • Certification: PMI SP
  • Total Questions: 325
  • Updated On: Jan 14, 2026
  • Rated: 4.9 |
  • Online Users: 650
Page No. 1 of 65
Add To Cart
  • Question 1
    • Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three. 

      Answer: B,C,D
  • Question 2
    • If you are the project manager of the BNQ Project and you add "waiting time" between two activities, then what have you added in the project? 

      Answer: A
  • Question 3
    • In which of the following group decision making techniques does the largest block in a group decide the group decision even if a bulk is not achieved? 

      Answer: D
  • Question 4
    • Which of the following techniques is used in businesses to determine the effect different costs or investments have on profit and other financial indicators? 

      Answer: C
  • Question 5
    • John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure:

      3

      Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days? 

      Answer: A
PAGE: 1 - 65
Add To Cart

© Copyrights DumpsEngine 2026. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsEngine.