Free PMI PMP Exam Questions

Absolute Free PMP Exam Practice for Comprehensive Preparation 

  • PMI PMP Exam Questions
  • Provided By: PMI
  • Exam: Project Management Professional
  • Certification: PMI PMP
  • Total Questions: 2069
  • Updated On: Nov 26, 2025
  • Rated: 4.9 |
  • Online Users: 4138
Page No. 1 of 414
Add To Cart
  • Question 1
    • A company is working on the prototype of a new contract document that includes visual elements. The product owner shared the project sponsor's feedback about the elements to be included, but the project team pushed back. However, when the project sponsor spoke with the team, they confirmed that all of the changes are possible. How should the project manager mitigate this situation?

      Answer: A
  • Question 2
    • A software development project is about to start. The product owner and project manager cannot agree on which programming language to use from the available two. The company lacks experienced developers in the product owner's preferred language; however, they are very skilled in the other language. What should the project manager do?

      Answer: A
  • Question 3
    • A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition. What should the project manager do next?

      Answer: A
  • Question 4
    • A project team is implementing a new solution that will be distributed worldwide. Due to a new issue that has a global impact, several government agencies are implementing new regulations that will affect the solution. The project manager must assess and prioritize the impact of these changes on the project scope/backlog. Which analytical tool can be used by the project manager to define this scenario? 


      Answer: A
  • Question 5
    • A project manager leads a project that implements a new process throughout the organization. The rollout is done in stages and the project manager planned a demonstration for the pilot business units. A manager from a business unit that is scheduled for a later date asks to be invited to the sprint review. What should the project manager do?


      Answer: C
PAGE: 1 - 414
Add To Cart

© Copyrights DumpsEngine 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsEngine.