Free NCARB Project-Management Exam Questions

Absolute Free Project-Management Exam Practice for Comprehensive Preparation 

  • NCARB Project-Management Exam Questions
  • Provided By: NCARB
  • Exam: ARE 5.0 Project Management (PjM) Exam
  • Certification: NCARB Certifications
  • Total Questions: 80
  • Updated On: Jan 14, 2026
  • Rated: 4.9 |
  • Online Users: 160
Page No. 1 of 16
Add To Cart
  • Question 1
    • The architect is on site to evaluate the completed work by the contractor. During the evaluation, the architect notices a structural connection that deviates from the contract documents. According to AIA B101, to which party should the architect report this observed deviation?


      Answer: D
  • Question 2
    • The architect's contract with the owner has a budget of construction cost, and the architect has established a budget of cost in the mechanical engineer's contract. The mechanical bid package is 36% over the budget. What is the engineer required to do?


      Answer: B
  • Question 3
    • What is the primary purpose of a construction schedule? 

      Answer: B
  • Question 4
    • During the preparation of the construction documents, it was noted that the survey inaccurately located the property line. Consequently, the parking layout had to be redesigned to fit within the corrected property boundary. The architect's additional costs and associated delay are the responsibility of which one of the following parties?


      Answer: A
  • Question 5
    • According to AIA Document B201, the architect must perform which of the following services during Construction Contract Administration? Check the three that apply. 


      Answer: C,E,F
PAGE: 1 - 16
Add To Cart

© Copyrights DumpsEngine 2026. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsEngine.